Operation of Pile Hammers and Pile Extractors on compressed air frequently presents problems of ice accumulation in valve assemblies and air passage ports. Icing is a function of temperature and humidity causing erratic equipment operation as, strange as it may seem, icing conditions occur at 85° as well as 32° if conditions are right.
There are several remedies for this problem which will help eliminate the icing condition:
- In your air line oiler, dilute your lubricating oil with an equal amount of ethylene glycol.
- Install in the air line between the Lubricator and the Hammer a Tanner De-lcer Tank. The Tanner De-lcer atomizes the anti-icing chemical into the airstream to prevent Hammer icing. Tanner gas equipment is available from Tanner Systems, Inc., Sauk Rapids, Minnesota 56379.
Always remember that in subfreezing weather it is essential to preheat the Hammer Cylinder prior to commencing daily operation. This is necessary to eliminate any frozen condensate inside the Cylinder and Valve. It is also to prevent possible cracking of the Cylinder due to thermal shock. During winter operation, it is advisable to be sure that all condensate is expelled from the Lubricator at the end of the shift so that it will not be allowed to freeze thereby plugging the oil suction line. It is also advisable to preheat the Lubricator to assure immediate lubrication when operations are commenced.
3 thoughts on “Vulcan Onshore Tip #63: Icing Conditions”